Suggestive Operating Procedures for Installation and Metering Connection of Grid Connected Solar Rooftop PV Systems by DISCOMs

A Suggestive Operating Procedures for Installation and Metering Connection of Grid Connected Solar Rooftop PV Systems by DISCOMs is proposed by MNRE under the Operational Guidelines.

[1] DISCOM to communicate to deficiencies to Consumer and provide an opportunity to resolve them;

[2] DISCOM may provide a window of 15 days for Consumer to resolve deficiencies found during the inspection;

[3] Joint Inspection by CEIG (if applicable) and DISCOM can reduce the timelines substantially. If DISCOM has no stock of meters, Consumer will purchase the same upon intimation by DISCOM. Inspection dates to be provided within 7 days by CEIG (if applicable) and DISCOM from the date of receipt of the request for inspection sent by Consumer;

[4] Joint Inspection by CEIG (if applicable) and DISCOM can reduce the timelines substantially.

 

The post ID for this chapter is 3582. For any suggestion or comment regarding the content, you may write to us at faqs[dot]solar[at]gmail[dot]com. Please quote the post ID in the subject, for better assistance.