Category-wise net cost for the consumer in Delhi under CAPEX model

The following are the capacity specific project cost payable by the consumer in Delhi under the CAPEX model

CAPEX Parts Project Cost per kWp (INR) Subsidy Amount per kWp (INR) Net Cost to Consumers per kWp (INR)
Part A 1 to 10 kWp 42,000 12,600 29,400
Part B >10 to 100 kWp 49,900 14,970 34,930
Part C > 100 kWp 47,000 14,100 32,900
Part D 1 to 10 kWp (Elevated) 42,000 + 700/metre 13,230 28,770 + 700/metre
Part E >10 to 100 kWp (Elevated) 51,000 + 1000/metre 16,200 34,800 + 1000/metre