Plant Installation

Intimation of Plant Installation by Installer

Once the Registration is approved, Installer proceeds to install the RTS Plant as per the approved drawings and equipment & safety standards. Once the installation is completed, Installer submits the intimation form and necessary documents under the ‘Intimation of Plant Installation’.

Actual Renewable Energy System Capacity installed (kWp)

Under this section the Installer updates the actual installed RTS plant capacity. In case the actual installed capacity is different from the approved capacity, Installer updates the actual plant capacity under the ‘Renewable System Details’. On doing so, Installer will have to submit the supporting documents pertaining to the actual installed capacity under the ‘Uploads’ section.

Minimum Equipment and Safety Standards – Goa Energy Development Agency

Under this section Installer is mandated to submit the acceptance that he has followed all the ‘Minimum Equipment and Safety Standards of Goa Energy Development Agency’. The standard format is printed on the letter head of the Installer and signed by Installer and Consumer on each page.The same is later uploaded to submit under the ‘Upload’ section of ‘Plant Installation’ stage.

Minimum Equipment and Safety Standards – Electricity Department Goa

Under this section Installer is mandated to submit the acceptance that he has followed all the ‘Minimum Equipment and Safety Standards of Electricity Department Goa’. The standard format is printed on the letter head of the Installer and signed by Installer and Consumer on each page.The same is later uploaded to submit under the ‘Upload’ section of ‘Plant Installation’ stage.

As- Built Renewable Energy System documents

In case the installer updates actual installed capacity different from the approved capacity, it will be required to submit the revised supporting documents¬† under ‘As-Built Renewable Energy System Documents’ under the ‘Uploads’ section. Installer will edit and upload the revised related registration documents w.r.t. the changes due to onsite execution.

Installer is also required to upload the PV Module and Inverter Warranty Certificates ,Post Installation Site Photographs (Date Tagged), PV Module serial numbers and Inverter serial numbers.

Details of the Meters Procured

As per present guidelines in the state of Goa, the procurement of net meter and solar meter along with test certificate is in the scope of consumer. Therefore after the meters are procured Installer on behalf of consumer submits the serial numbers of the meters and upload the test certificates in the ‘Details of Meters Procured’ under the ‘Uploads’ section.

On final submission of the ‘Intimation of Plant Installation’ form an intimation of plant installation completion gets forwarded to Goa Electricity Department and Goa Energy Development Agency for further assessment.